Week of February 2, 2026
Anticipated activities include:
- Continued test pitting activities
- Continued site preparations at substations
Week of February 8, 2026
Anticipated activities include:
- Continued test pitting activities
- Begin conduit installation activities (Willow Street)
- Continued site preparations at substations
For questions about the SHDF Project, call or text 631-237-7196
Visit www.Southampton2Deerfield.com
Email: info@southampton2deerfield.com